Started before the conflict but never completed,
in November 2002 works commenced to close off the
building externally and accommodate at the ground
floor the family medicine department with all required
treatment, training and administrative rooms. At
the beginning of 2003, the second floor was commenced
to accommodate a nurses training facility.
Technical assistant: |
LOUIS BERGER S.A. |
Contractor: |
UNIPROJECT of Kosovo |
Project Cost: |
750,000 € funded by
the European Union |
Programme Manager: |
Otto-Roman Barnert |